Answer:
Total cost= $10,400
Step-by-step explanation:
Giving the following information:
Month Number of snow cones Total operating costs
January 6400 5980
February 7000 6400
March 4000 4000
April 6900 6330
May 9000 8000
June 7250 6575
UNits= 12,000
First, we need to calculate the unitary variable cost and total fixed cost:
Variable cost per unit= (Highest activity cost - Lowest activity cost)/ (Highest activity units - Lowest activity units)
Variable cost per unit= (8,000 - 4,000) / (9,000 - 4,000)
Variable cost per unit= $0.8
Fixed costs= Highest activity cost - (Variable cost per unit * HAU)
Fixed costs= 8,000 - (0.8*9,000)
Fixed costs= $800
Fixed costs= LAC - (Variable cost per unit* LAU)
Fixed costs= 4,000 - (0.8*4,000)
Fixed costs= $800
Now, for 12,000 units:
Total cost= 800 + 12,000*0.8
Total cost= $10,400