Answer:
The EOQ is 516 Units
Step-by-step explanation:
Solution
Given that:
The product demand weekly is = 258 units
Standard deviation = 75 units
The cost of ordering is = 75
The time from receipt ordering = 3 weeks
The cost of procurement is = $10
The annual inventory cost (carrying ) is = 10%
Now,
The expected demand is = lead time demand * the lead time demand in weeks
= 258 units * 2 weeks = 516 Units