Answer:
Instructions are below.
Step-by-step explanation:
Giving the following information:
Standard Hours Standard Rate Standard Cost
Motor tune-up 2.50 $36.00 $90.00
230 tune-ups were completed during the week
Labor rate variance $ 900 F
Labor spending variance of $ 249 F
1) First, we need to calculate the actual hours:
Direct labor time (efficiency) variance= (Standard Quantity - Actual Quantity)*standard rate
249= (2.5*230 - actual quantity)*36
249= 20,700 - 36AQ
-20,451= -36AQ
20,451/36= Actual quantity
568= actual quantity
2) We need to calculate the actual rate:
Direct labor rate variance= (Standard Rate - Actual Rate)*Actual Quantity
900= (36 - Actual Rate)*568
900= 20,448 - 568Actual Rate
19,548/568= Actual Rate
$34.42= Actual Rate