Answer:
Cycle Time = 10.19482 minute
Step-by-step explanation:
From the question :
The Model E can be illustrated perfectly as shown below:
Process Time Required Predecessor Task Learning Rate
per Unit
A 9 82
B 12 A 86
C 18 B 81
D 9 C 90
E 12 D 80
F 17 E 88
G 14 F 83
H 12 G 85
I 8 H 82
Now For the minutes per week for each Process; we have :
Process Time Required Predecessor Learning Minutes
per Unit Task Rate (Week 16)
A 9 82 4.069096
B 12 A 86 6.564098
C 18 B 81 7.74841
D 9 C 90 5.9049
E 12 D 80 4.9152
F 17 E 88 10.19482
G 14 F 83 6.644165
H 12 G 85 6.264075
I 8 H 82 3.616974
The objective here is to determine the expected Cycle Time for Model E in Week 16
So, we can equally regard the Cycle Time = Bottleneck of Activity for Week 16.
Cycle Time = 10.19482 minute in as much as it is the the largest activity time for the week 16
Given that the demand per week is : = 247
The available time per week = 40 hours = 40 × 60 hours = 2400 minutes
Talk Time = Available Time Per Week/Demand Per Week
Talk Time = 2400/247
Talk Time = 9.716599
Thus; here the cycle time is greater than the talk time.