Answer:
Step-by-step explanation:
The solution is given below check the picture attached for better explanation
Direct labour rate variance:
=(Actual rate per hour-standard rate per hour)×actual hours
=($15-$15.50)×24 hours
=$12 F
2.
Direct labourTime variance:
=(Actual direct labour hour-standard direct labour hours)×standard rate per hour
={24-(200×.10)}×15.50
=$62 U
3. Total direct labour cost variance=direct labour rate variance+direct labour time variance
=310-360
=$50 U