Purchases= 17,200 pounds
Step-by-step explanation:
Giving the following information:
Production in units:
Month 1= 16,000 units
Month 2= 22,000 units
One pound of materials is required for each finished unit.
The inventory of materials at the end of each month should equal 20% of the following month's production needs.
Beginning inventory= 3,200 lbs.
To calculate the direct material required, we need to use the following formula:
Purchases= production + desired ending inventory - beginning inventory
Purchases= 16,000 + 22,000*0.2 - 3,200
Purchases= 17,200 pounds