Answer:
Total cost= $4,690
Step-by-step explanation:
Giving the following information:
Fixed costs= $430
Cost per job= $80
Cost per meal= $14
The company expected its activity in January to be 20 jobs and 190 meals.
The cost that would appear in the planned budget is calculated using the estimated activity.
Total cost= 430 + 80*20 + 14*190
Total cost= $4,690