Answer:
$281,000
Step-by-step explanation:
According to the scenario, computation of the given data are as follow:-
Total Cost Under the Weighted Average Method = Cost of Unit Transferred Out from the Department + Ending Work in Process Inventory
= $246,000 + $35,000
= $281,000
According to the analysis, In April the total cost to be accounted under the weighted-average method is $281,000.