Answer:
1.NPV of project A= $(69,014.48)
2.NPV of project B= $67,174.56
3.Project B should be accepted because it produces a positive NPV and would increase the wealth of the shareholders
Step-by-step explanation:
The Net present value (NPV) is the difference between the Present value (PV) of cash inflows and the PV of cash outflows. A positive NPV implies a good and profitable investment project and a negative figure implies the opposite.
NPV = PV of cash inflows - PV of cash outflows
PV of cash inflow= A × (1- (1+r)^(-n)/r
A-annul cash inflow, r- discount rate-15%
NPV of project A
Net present value of project A=
PV of cash inflow = 27,000× (1- 1.15^(-6)/0.15= 102,181.0327
PV of salvage value = $ 8,800 × 1.15^(-6)= 3804.482844
NPV = 102,181.0327 + 3804.482844 - 175,000= (69,014.48)
NPV = $(69,014.48)
NPV of Project B
PV of cash inflow = 44,000× (1- 1.15^(-6)/0.15= 166,517.2385
PV of working capital recouped = $175000 × 1.15^(-6)=75,657.32928
NPV = 166,517.23 + 75,657.32 - 175,000 = 67,174.56
NPV = $67,174.56
Recommendation
Project B should be accepted because it produces a positive NPV and would increase the wealth of the shareholders