Answer:
$270,000
Step-by-step explanation:
The computation of the initial outlay of the project is shown below:
The initial outlay of this project = Purchase Price of the Asset + Installation Costs + Shipping cost + Investment in Working Capital
= $200,000 + $15,000 + $5,000 + $50,000
= $270,000
We simply added the purchased price, installation charges, shipping cost and the investment in working capital so that the initial outlay could come