Answer:
The correct answer is option (b) 44,000
Step-by-step explanation:
Solution
Given that:
From the question given, the first step to take is to find out how many square feet would the Building Maintenance cost be allocated
Now,
The Square feet over which Building Maintenance cost would be allocated is stated as follows:
The Square feet over which Building Maintenance cost would be allocated = Square Footage of Machining + Square Footage of Assembly = 18000 + 26000
Thus,
=18000 + 26000 = 44,000