Answer:
Direct Labor Budget for 1st quarter $ 654480 for 2nd quarter $ 819072
Direct Labor Budget for 3rd quarter $ 1268640 for 4th quarter $ 1084320
Direct Labor Budget for 1st quarter 36360 hours for 2nd quarter 45504 hours
Direct Labor Budget for 3rd quarter 63432 hours for 4th quarter 54216 hours
Step-by-step explanation:
We multiply the production units with the direct labor hours per unit to get the total hours which are again multiplied with the wage rate to get the total direct labor wages.
SUNLAND, INC.
Direct Labor Budget
Quarter Quarter
1 2
Units Units
Production Budget 20,200 25,280
Direct Labor per unit 1.8 1.8
Total Hours 36360 45504
Wage Rates $ 18 $ 18
Direct Labor Budget $ 654480 $ 819072
SUNLAND, INC.
Direct Labor Budget
Quarter Quarter
3 4
Units Units
Production Budget 35,240 30,120
Direct Labor per unit 1.8 1.8
Total Hours 63432 54216
Wage Rates $ 20 $ 20
Direct Labor Budget $ 1268640 $ 1084320