60.1k views
1 vote
Bruce Corporation makes four products in a single facility. These products have the following unit product costs: Products A B C D Direct materials $ 15.10 $ 11.00 $ 11.80 $ 11.40 Direct labor 20.20 28.20 34.40 41.20 Variable manufacturing overhead 5.10 3.50 3.40 4.00 Fixed manufacturing overhead 27.30 35.60 27.40 38.00 Unit product cost $ 67.70 $ 78.30 $ 77.00 $ 94.60 Additional data concerning these products are listed below. Products A B C D Grinding minutes per unit 4.60 6.10 5.10 4.20 Selling price per unit $ 76.90 $ 94.30 $ 88.20 $ 105.00 Variable selling cost per unit $ 3.00 $ 2.00 $ 4.10 $ 2.40 Monthly demand in units 4,800 4,800 3,800 2,800 The grinding machines are potentially the constraint in the production facility. A total of 54,400 minutes are available per month on these machines. Direct labor is a variable cost in this company. How many minutes of grinding machine time would be required to satisfy demand for all four products? Multiple Choice 82,500 54,400 19,480 60,420

User Martin Lie
by
3.2k points

1 Answer

3 votes

Answer:

82,500

Step-by-step explanation:

The computation of the minutes of grinding machine required to satisfy demand is shown below

= (4,800 units × 4.60 + 4,800 units × 6.10 + 3,800 × 5.10 + 2,800 × 4.20)

= 22,080 + 29,280 + 19,380 + 11,760

= 82,500

We simply multiplied the Grinding minutes per unit with the Monthly demand in units and the same is to be considered above

User Tyson Hilmer
by
3.9k points