31.9k views
5 votes
The following data have been recorded for recently completed Job 323 on its job cost sheet. Direct materials cost was $2,057. A total of 37 direct labor-hours and 194 machine-hours were worked on the job. The direct labor wage rate is $24 per labor-hour. The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $33 per machine-hour. The total cost for the job on its job cost sheet would be:

1 Answer

2 votes

Answer:

Total cost of Job = $9,347

Step-by-step explanation:

The total cost of Job 323 would be the sum of the direct costs and the manufacturing overheads

Total cost = Direct material + direct labour + Overhead

The overhead absorption rate would be used to charge overhead to Job 323.

The absorbed overhead = OAR × actual machine hours used for Job 33

Total cost = 2,057 + (24× 37) + (194× 33) = $9,347

Total cost of Job = $9,347

User Manikanta Reddy
by
5.7k points