Answer:
1. 9.4 days
2. 9.4 days
3. 60%
4. 25.1 days
5. 5.2 days
Step-by-step explanation:
1. The Computation of throughput time is shown below:-
Throughput time = Process time + Inspection time + Move time + Queue time
= 3.4 + 0.7 + 1.1 + 4.2
= 9.4 days
2. The computation of Manufacturing Cycle Efficiency is given below:-
Manufacturing Cycle Efficiency Formula = Value added time (Process time) ÷ Manufacturing cycle time
Manufacturing cycle time = Process time + Inspection time + Move time + Queue time
= 3.4 + 0.7 + 1.1 + 4.2
= 9.4 days
Now, we will put into formula
So, Manufacturing Cycle Efficiency = 3.4 ÷ 9.4
= 0.4
3. The computation of percentage of the throughput time is shown below:-
= 1 - Manufacturing cycle efficiency
= (1 - 0.4)
= 60%
4. The computation of delivery Cycle Time is shown below:-
Delivery Cycle Time = Wait time + Throughput time
= 15.7 ÷ 9.4
= 25.1 days
5. The calculation of new manufacturing cycle efficiency is shown below:-
New MCE = Process time + Inspection time + Move time
= 3.4+0.7+1.1
= 5.2 days