Answer:
True
Step-by-step explanation:
Material Requirement Planning MRP can be run weekly, monthly or annually depending on the nature of business. This helps production managers to plan the capacity needs. Few organizations run MRP even on every 12 hours. If MTO has little variations the organization can run MRP twice a week but in the given scenario the MTO has lots of variations the organization should run MRP on daily basis and MTS has little variations the organization can run MRP weekly or biweekly.