Answer: 15 days
Step by step explanation:
It would take 20 days for 6 men to paint 4 walls because
half the people would mean double the time and 10 * 2 = 20
Because the 6 men are only painting 3 walls we would
get rid of a quarter of the time that it would take and 20 * 0.75 = 15