Answer:
NPV = 138,347.55
Step-by-step explanation:
Net Present Value (NPV) : This is one of the techniques available to evaluate the feasibility of an investment project. The NPV of a project is the difference between the present value of the cash inflows and the cash outflows of the project.
We sahall compute theNPV of this project by discounting the appropriate cash flows as follows:
Prevent Value of operating cash flow
PV =A× (1- (1+r)^(-n))/r
A- 23,900, r - 12%, n- 5
PV = $23,900 × (1- (1.12)^(-5))/0.05
=206,769.963
PV of Working Capital recouped
PV = 5600× 1.12^(-5)
= 3,177.59
NPV = initial cost + working capital + Present Value of working capital recouped + PV of operating cash inflow
NPV = (66,000) + (5600) + 3,177.59 + 206,769.96
NPV = 138,347.55