Answer:
Accepted and rejected
Step-by-step explanation:
Since the internal rate of return is 13.09% and the WACC is 12.68%
As we can see that the internal rate of return is higher than the WACC as WACC is considered as the discount rate
So the project should be accepted
And, if CAPM is used
So, the expected rate of return is
If CAPM is used
Risk-free rate of return + Beta × market risk premium
= 2.9% + 1.42 × 8.1%
= 2.9% + 11.502%
= 14.40%
And, The Internal rate of return = 13.09%
Since the internal rate of return is less than the expected rate of return therefore the project should be rejected