Sanchez Company's output for the current period was assigned a $419,000 standard direct labor cost. The direct labor variances included a $10,475 unfavorable direct labor rate variance and a $4,190 favorable direct labor efficiency variance. What is the actual total direct labor cost for the current period?

1 Answer

4 votes

Answer:

the actual total direct labor cost for the current period is $425,285

Step-by-step explanation:

Reconciling Standard Cost to Actual Cost

Standard Cost $419,000

Add Unfavorable direct labor rate variance $10,475

Less Favorable direct labor efficiency variance ($4,190)

Actual Cost $425,285