A bakery makes a limited number of croissants each day for sale in its coffee shop. The croissants cost $1.00 each to produce and sell for $2.00 each. Leftover croissants are sold in the bakery the following day for $0.60 each, and all of those are sold

The excess cost is:
The shortage cost is:
The optimal service level is

1 Answer

1 vote

Answer:

$0.40 ; $1 and $71.43%

Step-by-step explanation:

The computation is shown below:

Excess cost is

= Unit cost - Salvage Value

= $1 - $0.60

= $0.40

The shortage cost is

= Selling value - unit cost

= $2 - $1

= $1

And, the optimal service level is

= Shortage cost ÷ (Shortage cost + excess cost)

= $1 ÷ $1.60

= 71.43%

Basically we applied the above formulas