Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is scheduled to begin May 1, and a September 1 (17-week) completion date is desired. The condominium manager identified the following renovation activities and their estimated times:

Activity Immediate Predessor Time
A - 3
B - 1
C - 2
D A,B,C 4
E C,D 5
F A 3
G D,F 6
H E 4

a. Draw a project network.
b. What are the critical activities?
c. What activity has the most slack time?

User Werva
by
4.6k points

1 Answer

2 votes

Find the pictures in attachment

Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer-example-1
Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer-example-2