A project manager has determined that of the work for a project was completed in 9 days. How many more days will it take to finish the project if the work continues to progress at the same rate? 6 7 10
asked
Apr 13, 2021
225k
views
2
votes
A project manager has determined that of the work for a project was completed in 9 days. How many more days will it take to finish the project if the work continues to progress at the same rate?
6
7
10
21
27
Mathematics
middle-school
CHANist
asked
by
CHANist
4.5k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
2
Answers
1
vote
The Correct Answer Is 6
Swiffy
answered
Apr 14, 2021
by
Swiffy
5.2k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
4
votes
Answer:
its 21
Explanation:
just took the quiz
Artem Yevtushenko
answered
Apr 19, 2021
by
Artem Yevtushenko
5.4k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
5.7m
questions
7.5m
answers
Other Questions
Aliyah has $24 to spend on seven pencils. After buying them she had $10. How much did each pencil cost?
Evaluate a + b when a = –16.2 and b = –11.4 A. –27.6 B. –4.8 C. 4.8 D. 27.6
Can someone help me with 5??? ASAP?
Solve for h 3h=7(2/7-3/7h)-10
1/7 + 3/14 equivalent fractions
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org