Answer:
Allocation of Maintenance Department Cost
Personnel 1,000
Printing = 1,000
Developing = 3,000
Allocation of Personnel Department Cost
Printing = 2,600
Developing = 10,400
Step-by-step explanation:
Allocation of Maintenance Department Cost of $ 5,000
Personnel (1,000/5,000)×$ 5,000 = 1,000
Printing (1,000/5,000)×$ 5,000 = 1,000
Developing (3,000/5,000)×$ 5,000 = 3,000
Allocation of Personnel Department Cost of $12,000+$1,000 = $13,000
Printing (500/2,500)×$ 13,000 = 2,600
Developing (2,000/2,500)×$ 13,000 = 10,400