Answer:
$375,000
Step-by-step explanation:
The computation of the depletion expense for the first year is shown below:
= Total cost of a copper mine ÷ expected number of tons produced × extracted tons in the first year
= $3,000,000 ÷ 6,000,000 tons × 750,000 tons
= $375,000