The process of collecting detailed data on the work, then processing it in a computer system to arrive at an accurate representation of the current project status is called __________. a. Monitoring progress b. Updating the schedule c. Either A or B d. Neither A or B

User Huisinro
by
3.8k points

1 Answer

4 votes

Answer:

B: Updating the Schedule

Step-by-step explanation:

In project management, updating the schedule refers to updating the PM software with the work done, updating the state of play with resources, and the entering of important detailed data into the PM software that allows the project manager to monitor the work and also track the process. It allows the Project Manager to have an actual representation of the current project status.