90 men can complete a work in 24 days working 8 hrs a day. how many men are required to complete the same work in 18 days working 15/2 hrs a day

User NeARAZ
by
4.6k points

1 Answer

4 votes

Answer:

128 men

Explanation:

90 × 28 × 8 = M × 18 × 15/2

M = 128