A control chart is used to monitor a process mean by collecting sample means from that process on a regularly scheduled basis. The horizontal or "X" axis on this chart will represent the mean value of the sample while the vertical or "Y" axis will represent time measured in hours, days or weeks.

O True
O False

User LeMimit
by
3.2k points

1 Answer

3 votes

Answer:

True

Explanation:

A control chart is used to monitor a process mean by collecting sample means from that process on a regularly scheduled basis. The horizontal or "X" axis on this chart will represent the mean value of the sample while the vertical or "Y" axis will represent time measured in hours, days or weeks.

The answer is True.