Answer:
c) Under applied overheads =$10,000
Step-by-step explanation:
Overheads are charged to units produced by the means of an estimated overhead absorption rate. This rate is computed using budgeted overhead and budgeted activity level.
As a result of this, overhead charged to total units product might be over or under absorbed compared to the actual amount incurred.
Overhead absorption rate
=budgeted Overhead/Budgeted labour cost × 100
= $300,000/150,000 × 100
= 200% of direct labour cost
Applied overhead= OAR× actual labour cost
= 200% × $170,000
=$ 340,000
Under applied overhead = is the difference between actual overhead and absorbed
$330,000 - $340,000 = $10,000
Here it is under applied because the applied is less than the actual overhead cost