Answer:
$25,000
Step-by-step explanation:
The activity was supposed to be performed by the subcontractor for 20 weeks at an anticipated cost of $100,000.
If the subcontractor informs us that the activity can be completed in 16 weeks for $200,000, then the implication is that the change (slope) in the activity is: Change in cost / Change in time = ($200,000 - $100,000) / 20 weeks -16 weeks = $25,000