Solution and Explanation:
(a)-NPV if the Discount Rate is Zero
If the Discount Rate is Zero, the NPV of the Project is the sum of the Future cash flows deducted by Initial Investment
Net Present Value (NPV)
= $256,430
If the Discount Rate is Zero, The NPV will be $256,430”
(b)- NPV If the discount rate is infinite
If the Discount Rate is Infinite, the NPV of the Project is the Initial Investment
NPV = -$534,800 (Negative)