A quality engineer notes that a process produces data that are binomial and has been obtained using a sample space that is constant. The primary interest of the process manager is in the percentage of bad parts. An appropriate control chart to use would be a(n) ________.

User Justinl
by
5.0k points

1 Answer

0 votes

Answer:

A U chart.

Step-by-step explanation:

The U chart is used in statistical quality control to observe 'count' data type for situations where the sample size is above 1.

The U chart speculates that the size or number of units to be inspected may vary due to the possibility of counting nonconformities.