Answer:
1. Total direct labor: $192,000
2. Total factory overhead budget: $555,600
Step-by-step explanation:
1. Total direct labor
Addison Co.
Direct labour budget for the second quarter
Budgeted production units 2,400
Direct labor hour per one unit 4
Total direct labor hour needed 9,600
Cost per one direct labor 20
Total direct labor $192,000
2. Total factory overhead budget:
Addison Co.
Factory overhead budget for the second quarter
Total direct labor hours needed 9,600
Variable rate per direct labor 11
Budgeted variable overhead $105,000
Budgeted fixed overhead $450,000
Total factory overhead $555,000