Answer:
Direct labor budget= $858,000
Step-by-step explanation:
Giving the following information:
The budgeted production is for 52,000 comforters in 2012. Each comforter requires 1.5 hours to cut and sew the material. If cutting and sewing labor costs $11.00 per hour.
First, we need to calculate the total requirement of direct labor hours:
Total direct labor hours= 52,000 units*1.5= 78,000 hours.
Direct labor budget= 78,000 hours* $11= $858,000