Answer:
The no. of days required to finish the work = 10 days
Explanation:
In first case :-
No. of workers
= 10
No. of days
= 5
No. of hours taken
= 2 hours
In second case :-
No. of workers
= 2
No. of days
= ??
No. of hours taken
= 5 hours
We know that
⇒
=
![H_(2)](https://img.qammunity.org/2021/formulas/chemistry/middle-school/4o51dyeoin39yit8t1fdsgrko2kss60roh.png)
⇒ Put all the values in above formula we get
⇒ 10 × 5 × 2 = 2 ×
× 5
⇒
= 10 days
Thus the no. of days required to finish the work = 10 days