Emily has recently learned that she needs to reduce the duration of her project to meet an imposed deadline. She has calculated the crash cost per unit and knows the maximum units each activity can be reduced. What is the next step?A. Find the activity with the lowest crash cost B. Calculate the optimum cost-time point C. Calculate the crash point D. Identify the critical path E. Find the activity with the highest crash cost

User Nvrtd Frst
by
4.8k points

1 Answer

5 votes

Answer:

Identify the critical path.

Step-by-step explanation:

Critical path is the sequence of project network activities which add up to the longest overall duration. It also helps to determine the shortest time possible to complete the project.

Therefore,

For Emily to meet up with imposed deadline, she needs to Identify the critical path and reduce the activities along the critical path.