Answer:
WIP = 1.25
As here 1 plane either on the runway or waiting to take off
Step-by-step explanation:
given data
time between airplane takeoffs = 3 min
run time runway = 45 seconds
average waiting take off = 4 minutes and 15 seconds
solution
we know that here
WIP = TR × TT .........................1
here WIP is number of plane waiting or on the runway
and TR is number of planes taking off per hour and TT is time for waiting and the runway
so here TR is 15 plans per hour.
and
TT =
hr =
hr
so put value in equation 1 we get
WIP = 15 ×
WIP = 1.25
so here is 1 plane either on the runway or waiting to take off