Answer:
Activity expected duration = 2.333
Step-by-step explanation:
Given:
Optimistic (a) = 1
Most likely (m) = 2
Pessimistic (b) = 5
Activity’s expected duration = ?
Computation of Activity expected duration:

Activity expected duration = [1 + 4(2) + 5] / 6
Activity expected duration = [1 + 8 + 5] / 6
Activity expected duration = [14] / 6
Activity expected duration = 2.333