An activity on a project schedule has these duration estimates: optimistic (a) = 1, most likely (m) = 2, and pessimistic (b) = 5. The activity’s expected duration is:

User Ory Band
by
6.0k points

1 Answer

6 votes

Answer:

Activity expected duration = 2.333

Step-by-step explanation:

Given:

Optimistic (a) = 1

Most likely (m) = 2

Pessimistic (b) = 5

Activity’s expected duration = ?

Computation of Activity expected duration:


Activity\ expected\ duration = ((a + 4m + b))/(6)

Activity expected duration = [1 + 4(2) + 5] / 6

Activity expected duration = [1 + 8 + 5] / 6

Activity expected duration = [14] / 6

Activity expected duration = 2.333