Answer: Costs of units started and completed: you will take the equivalent units calculated for units started and completed x the cost per equivalent unit for materials, labor and overhead (or conversion). The sum of these 3 will be the cost of units completed and transferred which is also known as cost of goods manufactured
Step-by-step explanation: