Final answer:
The project should be accepted since it has an NPV = $15,391.23.
Step-by-step explanation:
To determine whether the project should be accepted, we need to calculate the net present value (NPV) of the project. The NPV is calculated by finding the present value of each cash flow and subtracting the initial cost of the project. In this case, the initial cost is $91,000 and the cash flows are $11,000 per year for 20 years. Using a discount rate of 8%, the NPV is:
NPV = -$91,000 + ($11,000 / 1.08)1 + ($11,000 / 1.08)2 + ... + ($11,000 / 1.08)20
After calculating the NPV, we find that it is approximately $15,391.23. Therefore, the correct answer is:
A. Yes, the project should be accepted since it has an NPV = $15,391.23.