Martha works as a project manager at a bank. Due to certain changes in external factors, Martha needs to make a few alterations in the tactical goals of her project. In such a scenario, which of the following will best help Martha cope with the change?

(A) Negotiation
(B) Motivation
(C) Project environment knowledge
(D) Soft skills

User Mceo
by
5.0k points

1 Answer

3 votes

Answer:

The correct answer is letter "C": Project environment knowledge.

Step-by-step explanation:

Project environment knowledge is the information that managers must consider about the surrounding environment where their businesses operate to find out opportunities and threats to take advantage of them or mitigate them when they arise. Managers must keep an open sight of the events happening in the immediate atmosphere of the entity and the overall world to adjust their plans as necessary.