Answer:

Leveling

Step-by-step explanation:

Leveling, also called Resource Leveling, is a project management strategy that disregards the allocation of resources and addresses possible conflicts resulting from over-allocation.

Whenever a project is performed by project managers they will have to prepare their resources appropriately.

The company would profit from it without having to suffer problems and being unable to meet the deadline.

It is regarded as one of the organisation's key aspects for resource management.