Answer:
Variable cost= $73.50
Step-by-step explanation:
The high low method is used to get the fixed and variable cost of a business activity given limited data. It involves taking the highest and lowest points, then comparing the total cost at these points.
We use the following formula
Variable cost= (Highest activity cost - Lowest activity cost)/ (Highest activity unit - Lowest activity unit)
Variable cost= (207,250- 97,000)/ (5,900-4,400)
Variable cost= 110,250/ 1,500
Variable cost= $73.50