In slab placement, what comes directly before concrete floating? Select one: a. Formwork placement b. Curing c. Troweling d. Pouring e. Strike-off

1 Answer

5 votes

Answer:

e. Strike-off

Step-by-step explanation:

  • The precast suspended slabs are considered by pouring the slabs in a framework of the slabs and then lifting the slabs into suspended postilions in the structure.