Answer:
a. $230,000
b. $690,000
c. $710,000
Step-by-step explanation:
The computation is shown below:
a. Cost of direct material used = Beginning balance of raw material + purchase made - ending balance of raw material
= $140,000 + $220,000 - $130,000
= $230,000
b. Total manufacturing cost
Total manufacturing cost = cost of direct materials used + direct labor cost + overhead cost
= $230,000 + $150,000 + $310,000
= $690,000
c. Cost of goods manufactured
Cost of goods manufactured = Beginning balance of Work in process + Manufacturing cost - Ending balance of Work in process
= $90,000 + $690,000 - $70,000
= $710,000