An incurred cost that cannot be recovered, which is irrelevant for all decisions about the future, is included in the projected cost of a project. According to "Thinking Like an Economist," this an example of:_____________.

User Robaker
by
4.3k points

1 Answer

3 votes

Answer:

An incurred cost that cannot be recovered, which is irrelevant for all decisions about the future, is included in the projected cost of a project. According to "Thinking Like an Economist," this an example of: Failing to ignore sunk costs

Step-by-step explanation:

A sunk cost is a cost that cannot be recovered or changed and is independent of any future costs a business may incur. Since decision-making only affects the future course of business, sunk costs should be irrelevant in the decision-making process