Answer: The correct answer is "a. the linking of risks with specific vendors ".
Explanation: All of the following are claims that Microsoft makes about the risk management capabilities of Microsoft Project EXCEPT the linking of risks with specific vendors.
Microsoft states that in addition to monitoring the process to manage projects in a much more efficient manner, a risk probability and impact must be specified to assign properties to these risks.
But Microsoft does not claim anything about linking risks with specific suppliers.