Answer: 15 hours
Explanation:
Given : Patrick, by himself, can paint four rooms in 10 hours.
i..e Time taken by Patrick to paint the 4 walls = 10 hours.
Since rate of work =
![(Work)/(Time)](https://img.qammunity.org/2021/formulas/mathematics/high-school/7hqt00atzkpy8s409q4gkwiww8ikh0sopl.png)
We consider the entire job as 1.
Then, the rate of work done by Patrick =
![(1)/(10)](https://img.qammunity.org/2021/formulas/mathematics/middle-school/s1nk8ftomqwqljr3bnh1epjpogskrs6plr.png)
If he hires April to help, they can do the same hob together in 6 hours.
i.e. the rate of work done by Patrick and April together =
![(1)/(6)](https://img.qammunity.org/2021/formulas/mathematics/middle-school/t6mk2mfk5g8w2jv7s83cjb4sbxcq55r7z0.png)
Then, the rate of work done by April = rate of work done by Patrick and April together - rate of work done by Patrick
![(1)/(t)=(1)/(6)-(1)/(10)\\\\\Rightarrow\ (1)/(t)=(10-6)/(60)=(4)/(60)\\\\\Rightarrow\ (1)/(t)=(1)/(15)\\\\\Rightarrow\ t=15](https://img.qammunity.org/2021/formulas/mathematics/high-school/98oehldi8xbato6e3stet4nnadw6loqi3s.png)
Hence,it will take 15 hours April to paint four rooms .