The project management plan

A. Includes business documents internal to the project.
B. Is tailored to the specific project.
C. Includes project documents.
D. Is an output of the project.

1 Answer

4 votes

Answer: The correct answer is "C. Includes project documents".

Explanation: A project plan is a document that is normally used by managers to guide the execution and control of the project. In addition, it contains documents, assumptions of decision-making and all other information that helps expedite communication between the parties that make up the project and defines the scope, costs and objectives of the project.