Answer:
The correct answer is B.
Step-by-step explanation:
Giving the following information:
The company uses the activity rates to assign overhead costs to products:
Processing customer orders $96.63 per customer order
Assembling products $2.45 per assembly hour
Setting up batches $58.89 per batch
Last year, Product F76D involved 9 customer orders, 436 assembly hours, and 26 batches.
Allocated overhead= 9*96.63 + 436*2.45 + 26*58.89= $3,469.01